March Consulting Associates Inc. > Projects > Safe to Operate Analysis & Strap Beam Design for Potash Silos – Mosaic K1 & K2

Safe to Operate Analysis & Strap Beam Design for Potash Silos - Mosaic K1 & K2

March completed the safe to operate analysis on six 100 ton silos at Mosaic’s K1 & K2 sites. This analysis was completed to ensure that the silos were safe from sudden catastrophic failure. March completed this analysis and reported on the current conditions of the silos based on operating parameters. In addition to the analysis, March also completed the design for silo strap beams and utilized site visual inspections and UT thickness reports to determine suitable locations for the additional strap beams.

March is here to help. Let's get started on your next project.

Contact Us